Timeline · Bengaluru

How long a 3 BHK interior takes in Bengaluru

Sixty days from design sign-off, and about three weeks before that to get to sign-off. Here is the whole programme, week by week, and the four things that actually cause delay.

The short answer

Sixty days, from the right starting point.

A 3 BHK fit-out in Bengaluru takes about 60 working days from design sign-off to handover. The number people get wrong is what comes before that: two to three weeks of design, measurement and material selection, which is driven almost entirely by how quickly decisions get made. So from first meeting to moving in is realistically 11 to 13 weeks. Working days matter here. Most apartment associations permit weekday work only, so 60 working days is roughly 12 calendar weeks, not eight.

The programme

Week by week.

StageDurationWhat happens
Design and selection2–3 weeksSite measure, layouts, 3D views, material and hardware selection, itemised quote
Sign-offDrawings and quote frozen. The 60-day clock starts here
Site prep and demolitionDays 1–7Protection, demolition, debris out, association formalities complete
Civil and plumbing first fixDays 5–18Wall changes, concealed plumbing, waterproofing in wet areas
Electrical first fixDays 12–24Conduit, boxes, new circuits, DB work
False ceilingDays 20–32Framing, boarding, first coat
Factory productionDays 8–35Runs in parallel, cutting, edge banding, pre-assembly
PaintingDays 30–45Putty, primer, finish coats
Modular installationDays 38–52Kitchen, wardrobes, storage, media and study units
Second fix and finishesDays 48–56Switches, lights, sanitary fittings, mirrors, hardware
Snagging and handoverDays 56–60Documented pre-handover check, snags closed, clean, handover

Factory production overlapping the site trades is what makes 60 days possible at all. A fully site-built home of the same scope runs closer to 90.

What causes delay

Four things, in order of frequency.

01

Decisions after sign-off

Changing a shutter finish in week five means re-cutting panels already made. Every change after sign-off is re-quoted with a time impact stated, and this is the single most common cause of a missed date.

02

Association restrictions discovered late

Weekday-only work, a 6pm cut-off and a booked service lift are all manageable when planned. Discovered in week one, they cost a week.

03

What the walls were hiding

Plumbing in worse condition than it looked, damp that needs treating, an electrical load that will not carry air conditioning. This is why we survey before committing to a date.

04

Client-supplied items arriving late

A hob, a chimney or a sanitary set bought separately and delivered in week nine holds up second fix. If you are supplying items, we will give you the date they are needed by.

Questions

Asked and answered.

For a 2 BHK with a straightforward scope, yes. For a 3 BHK it means either reducing scope or accepting compression that raises the risk of snags. We would rather commit to 60 and hold it than promise 45 and miss.

If the delay is within our control we credit ₹1,000 for every day against the final invoice. If it is caused by a change you requested after sign-off, we re-quote the time before doing the work so nobody is surprised.

For a full 3 BHK fit-out, generally no. The wet trades, dust and the fact that every room is in use at some point make it impractical. Room-by-room phased work is possible and adds roughly three weeks.

At design sign-off, when drawings and quote are frozen and the advance is received. Not at first enquiry, because the design stage runs at the speed of your decisions rather than ours.

Want a number for your own home?

The calculator gives an itemised estimate in about two minutes. The site measurement and the first consultation are free either way.

Written and checked by the Interiors by Archree design team in Bengaluru. Figures come from our own rate card and quoted projects, not from industry averages. Last updated 27 August 2026. Found something wrong? Tell us and we will correct it.

Plywood grades quoted here follow IS 303 (BWR) and IS 710 (BWP, marine grade), and every estimate is exclusive of the 18% GST that applies to modular work. What these grades and terms actually mean →