Plumbing before waterproofing
Every pipe position has to be final before the membrane goes on, because each penetration needs individual sealing. A pipe moved afterwards means cutting the membrane you just paid for.
14–21 daysTypical job
The smallest room in the house and the most technical. Get the sequence wrong and the flat below finds out first.
A full bathroom renovation in Bengaluru costs ₹85,000 to ₹3.5 lakh per bathroom. A standard 40 sq ft bathroom with mid-range fittings runs ₹1.3–₹1.8 lakh, including demolition, waterproofing, plumbing, tiling, fittings and a false ceiling.
Five stages, and every failure comes from compressing one of them.
Every pipe position has to be final before the membrane goes on, because each penetration needs individual sealing. A pipe moved afterwards means cutting the membrane you just paid for.
We flood the floor for 48 hours and watch the ceiling below. If it fails, we redo it while it is still accessible. Testing after tiling means breaking a finished floor.
Not with a spirit level — with a bucket. Water should reach the drain in seconds and leave no puddle. A bathroom that ponds will stain, smell and eventually leak whatever membrane is underneath.
We sequence bathrooms one at a time in a multi-bathroom home. In a single-bathroom flat we will tell you honestly that you need somewhere else to be for about a week.
Renovation failures are almost always sequencing or preparation, not materials.
The wall-to-floor corner is where bathrooms leak. Rounded and mesh-reinforced before any membrane goes on.
1.2m on general walls, floor to ceiling in the wet zone. Splash travels much higher than people expect.
CPVC hot and cold lines tested at 6 bar before the wall is closed. Finding a leak after tiling means breaking a finished wall.
We will not lay a polished tile on a bathroom floor regardless of how it looks in the showroom.
Sequenced so nothing has to be done twice.
A site visit that records what is actually there, not what the plan says. Older buildings hide surprises and we would rather find them before quoting than after starting.
Civil, plumbing, electrical, waterproofing, then finishes. Renovation goes wrong when trades overlap in the wrong order, and that order is not negotiable.
One project manager, one WhatsApp group, daily photographs. You know what happened on site every day without having to ask.
Snag list closed in writing, debris cleared to the building's designated point, and every warranty document handed over together.
Per bathroom, complete. Sanitaryware and fittings are itemised separately.
Retile and re-waterproof with existing plumbing positions retained.
Full strip-out, new concealed plumbing, waterproofing, tiling and false ceiling.
Complete rebuild with layout change, premium fittings, glass partition and niche detailing.
| What you get | Essential | Premium | Luxe |
|---|---|---|---|
| Starting price | ₹85,000 | ₹1.6L | ₹3.5L |
| Demolition and disposal | Yes | — | — |
| Waterproofing with ponding test | Yes | — | — |
| Floor and wall tiling | Yes | — | — |
| Basic false ceiling | Yes | — | — |
| Full strip-out | — | Yes | — |
| New concealed CPVC plumbing | — | Yes | — |
| Full-height shower waterproofing | — | Yes | — |
| Grohe-class fittings | — | Yes | — |
| Ventilated false ceiling | — | Yes | — |
| Layout change | — | — | Yes |
| Glass shower partition | — | — | Yes |
| Recessed niches | — | — | Yes |
| Premium sanitaryware | — | — | Yes |
| Written warranty | — | — | Yes |
Sanitaryware, taps and shower systems are quoted separately so you can choose freely and compare honestly.
₹85,000 to ₹3.5 lakh per bathroom. A standard 40 sq ft bathroom with mid-range fittings runs ₹1.3–₹1.8 lakh complete, including demolition, waterproofing, plumbing, tiling and a false ceiling. Sanitaryware is separate.
14 to 21 days. The parts that cannot be compressed are the waterproofing cure and the 48-hour ponding test before tiling. Anyone promising a bathroom in a week is skipping one of them.
Within limits. Moving a basin or shower is usually fine. Moving the WC significantly means changing the drain connection to the stack, which needs association approval and is often refused. We check this before quoting rather than after.
Yes. Lifting the floor destroys whatever membrane was under it. Retiling a bathroom without re-waterproofing is the most expensive shortcut in home renovation, because the damage appears in the flat below.
Then you need somewhere else to be for roughly a week of the 14–21 days. We will say that plainly rather than pretend the bathroom stays usable — it does not, once the floor is up.
We work across Bengaluru, and we quote after seeing the site — never over the phone.
Including the ceiling of the room below, if you can. That tells us whether this is a renovation or a repair.
Written on-time guarantee · 10-year warranty
Free consultation + 3D design of your own floor plan. Fill in to unlock the offer.
No spam. Your number stays private. By continuing you agree to our Terms & Privacy Policy.