How to read an interior design quotation

Where quotes hide money, which lines to insist on, and the six questions that make two quotations genuinely comparable.

The short answer

A quote you cannot audit is a quote you cannot compare.

A usable interior quotation prices work by measure, running feet of shutter, square feet of loft, count of electrical points, not by room as a lump sum. It names the material and the brand for every line, states GST separately, lists what is excluded, and ties payments to stages rather than to dates. If a quotation gives you "Kitchen, ₹3,20,000" and nothing else, it is not hiding anything clever; it simply cannot be checked, which means the number can move later without anyone being able to say it did.

The checklist

Six questions, in the order to ask them.

01

Carpet area or built-up?

Built-up can be 20–30% larger for the same work. Every per-square-foot comparison is meaningless until this is settled.

02

Is GST inside or outside the number?

A ₹10 lakh exclusive quote is ₹11.8 lakh. Side by side with an inclusive quote it looks 15% cheaper and is not.

03

Which board, which grade, where?

"Plywood" is not a specification. BWR or BWP, IS 303 or IS 710, and which one is at the sink base, see the plywood guide.

04

Which hardware, by name?

Hinges and channels are 15–20% of a kitchen. "Soft-close hardware" spans a four-fold price range. A brand and a series, or it is not priced.

05

Is civil and electrical in or out?

Rerouting plumbing and adding points can be ₹1–2 lakh with nothing to do with finish. This is the most common silent exclusion.

06

What happens if it runs late?

A date with no remedy behind it is a hope. Ours carries ₹1,000 a day; whatever the answer, get it in the contract.

Line by line

What a proper line item looks like.

WeakAuditable
Kitchen, ₹3,20,000Base units 14 rft @ ₹X/rft. BWR carcass IS 303, HDHMR shutters, Hettich soft-close
Wardrobes, ₹2,40,000Wardrobe 8 rft x 7 ft @ ₹X/sft. BWR carcass, laminate shutters, loft 8 rft @ ₹Y/sft
Electrical work, ₹85,00042 points @ ₹X/point, 3 new circuits, DB upgrade, itemised by type
False ceiling, ₹1,10,000320 sft gypsum @ ₹X/sft, 18 recessed fittings supplied by client
Painting, lump sum1,850 sft @ ₹X/sft, putty, primer, two coats, brand and sheen named

The right-hand column is not longer for the sake of it. Every one of those lines can be measured on site after installation, which means the quote is a document you can hold someone to rather than a proposal.

The exclusions

Read this section first, not last.

The exclusions list is the most informative part of any quotation and it is usually the smallest text on the last page. Read it before the prices. Appliances, loose furniture, curtains, structural work, statutory approvals and society charges are commonly excluded and reasonably so, what matters is that they are named, so you can budget for them rather than discover them.

A quotation with no exclusions section at all is the one to worry about. Everything has exclusions; a document that does not state them has simply moved the conversation to later, when you have less leverage.

Questions

Asked and answered.

Two carefully compared beats five skimmed. Normalise them first, same area basis, same GST treatment, same inclusions, and very often the ranking changes once you do.

Not automatically. It is a problem when it is cheapest because something is missing rather than because someone is more efficient. Normalising the exclusions tells you which it is.

Staged against progress, commonly 50% at order confirmation, 40% before dispatch or installation, 10% after handover. The final tranche is the part that matters. It is your only leverage on snags.

You can, and you should treat what you get as a budget range rather than a price. Anything firm before a site measurement will be revised, particularly on civil and electrical.

Want a number for your own home?

The calculator gives an itemised estimate in about two minutes. The site measurement and the first consultation are free either way.

Written and checked by the Interiors by Archree design team in Bengaluru. Figures come from our own rate card and quoted projects, not from industry averages. Last updated 27 August 2026. Found something wrong? Tell us and we will correct it.

Plywood grades quoted here follow IS 303 (BWR) and IS 710 (BWP, marine grade), and every estimate is exclusive of the 18% GST that applies to modular work. What these grades and terms actually mean →